Metro Plouffe Waterloo

Project summary
The Metro Waterloo project involved a 9,000 sq. ft. expansion, repairs to the exterior facades, renovations throughout the existing store and a major overhaul of the parking lot. The project was carried out in several phases to ensure that the store would remain open to customers despite the work.
Activity sector
Commercial
Budget
5M$ to 10M$
Surface area
34 300 ft2
Schedule
± 52 Weeks
Realisation date
2022
Challenge
The store had to remain open to customers during the work. This required extraordinary coordination and collaboration from all parties involved throughout the project. The construction team, the customer and the professionals met on a weekly basis for most of the project to monitor progress and carefully plan future phases.